Future Installs (Next 30 - 60 Days)
Installation
In the coming 30 - 60 days, Ting will begin installations in Nodes 7, and 12 in the Southeast Work Zone near Gates 4 and 1. Also Nodes 13 and 18 in the Northeast Work Zone near gate 5. If you are in one of these nodes be on the lookout for additional communications coming from Ting. Our team looks forward to bringing fiber internet right to your door. If you have not already done so please verify that Resident Services has your current email and telephone number. Ting will rely on this contact information to schedule your installation.
February 23, 2026
Installation
Current Installs
Installation
Ting is now actively installing services to residents of Laguna Woods Village. Currently residents living in Nodes 8, 9, and 11 in the Southeast Work Zone between Gates 1 and 3 and Nodes 1, 2, 3, 4, 5, and 6 also in the Southeast Work Zone surrounded by Gates 2, 3 and 4 will have already received notifications. Our team will be reaching out to schedule your installation or may have already done so. We’re excited to bring you the benefits of blazing-fast fiber internet.
February 23, 2026
Installation
Future Construction (Next 30 - 60 Days)
Construction
Over the next 30 - 60 days, Ting construction will begin in Node 12 near Gate 1 in the Southeast Workzone and Nodes 16, and 17 in the Northeast Work Zone outside of gate 6. Work will also be starting in the West Workzone between Gates 10 and 7. Our crews will be preparing these neighborhoods for the arrival of fiber internet. We’ll work efficiently to minimize disruptions while building the network that will soon bring next-generation connectivity to your community.
February 23, 2026
Construction
Current Construction
Construction
Ting construction crews are hard at work in Laguna Woods Village, with active builds underway in Nodes 1, 3, 5, 6, 7 and 10 in the Southeast Work Zone near Gates 2, and 4. In addition Nodes 13, 14, 15 and 18 in the Northeast Work Zone near Gate 5. Residents in these areas may notice construction activity, including pre-wiring of buildings, as we prepare the infrastructure for fiber internet service. We appreciate your patience during this exciting progress toward faster, more reliable connectivity.
February 23, 2026
Construction
PC Club Event
Events
Stop by the PC Club event at Clubhouse 7 on February 10 at 4:30 p.m. for friendly, informative conversation focused on updates, timelines, and the most common questions residents have. Whether you’re fully caught up or feel a step behind, you’ll leave with a better idea of what to expect and who to contact if you need help.